Go top
Project information

Measurements of power supply quality in the regasification plant of Reganosa in Mugardos

L. Rouco P. García-González

June 2006 - September 2006

Funding entity Reganosa


The aim of this project is the measurement of power supply quality in the regasification plant of Reganosa in Mugardos. The power supply quality will be evaluated measuring voltage sags, slow voltage variations, flicker and harmonics. It will be carried out with a LEM Topas 2000 equipment that will be installed in the secondary windings of the voltage transformers connected at the 132 kV busbars of Reganosa substation.


ReganosaMedidas